Blue Devil I / II
Multi-INT ISR · BIG SAFARI ecosystem · cancelled airship
ADJACENT programme
Block I: King Air C90s with WAMI + SIGINT + FMV in Afghanistan. Block II: same sensor idea on a 5–7 day airship; stopped 2012; hardware to Greenville. Residual parts absorbed into other Air Force programmes.
Blue Devil Block I flew an integrated pod (wide-area imagery, night imagery, FMV, SIGINT cueing) on contractor King Air C90s. NSA and JIEDDO supported it; a SIGINT intercept could cue WAAS then narrow-FOV video. PED used NSA-Net, Trojan Spirit SATCOM and DIA VSAT. SAIC contract FA8650-10-C-1887 grew to ~$243.5m by August 2013. Block II (MAV6 contract FA8620-11-C-4024, initially $86.2m, 14 March 2011) tried to put the architecture on a 5–7 day airship with Payload Integration Infrastructure, ground station, onboard processing and mission payload. Payload integration stopped 4 January 2012; airship work ended May 2012; ~$149m spent. Equipment shipped Q4 FY2012 to BIG SAFARI storage, Greenville, Texas. DODIG-2013-128: residual components absorbed into other Air Force programmes. Whether any of that hardware became Orion GFE is OPEN.
Sources
- DODIG-2013-128
- AFCEA, 1 Feb 2013, Blue Devil sensor integration
Related
645 AESG / BIG SAFARI
USAF rapid acquisition and special-mission integration
Gorgon Stare
645 AESG wide-area airborne surveillance for MQ-9
Where did Blue Devil residual components go?
DODIG-2013-128 — Blue Devil Block 2
DoD Inspector General · 19 September 2013 · 54 pages · Drive source copy
Blue Devil II stopped; hardware to Greenville
Payload stop 4 Jan 2012 · pack-out May 2012 · storage Q4 FY2012
Greenville, Texas
BIG SAFARI short-term storage · Blue Devil II hardware
Blue Devil, MAGIC, Orion, BIG SAFARI — 2014 window